Mitsui Fudosan’s First Residential Development Project in Seattle, U.S.
Completion of West Edge Tower
(Previously Named 2nd & Pike)

June 27, 2018
Mitsui Fudosan Co., Ltd.

Key Points of the Release

  • Completion of West Edge Tower (previously named 2nd & Pike), Mitsui Fudosan’s first residential development project in Seattle
  • High-rise residential building with 39 floors above ground, 5 floors below ground and enjoying views of Elliott Bay and Mount Rainier from the upper floors
  • The Mitsui Fudosan Group’s long-term management policy, Vision 2025, includes the aim to evolve into a global company, and dramatic growth overseas is expected in the future

Tokyo, Japan, June 27, 2018 - Mitsui Fudosan Co., Ltd., a leading global real estate company headquartered in Tokyo, completed overall development on West Edge Tower (previously named 2nd & Pike) in April 2018. The work was conducted through U.S. subsidiary Mitsui Fudosan America, Inc. and is the Mitsui Fudosan Group’s first residential development project in Seattle. Mitsui Fudosan has 8 rental housing projects and properties (4 under development and 4 completed) containing approx. 2,500 units in total across the U.S.

This property is in Seattle, which has grown remarkably among major U.S. cities in recent years, and is centrally positioned in an office district with skyscrapers and stores including luxury department stores. This ideal location is in the close vicinity of Pike Place Market, visited by many locals and tourists, while spectacular views can be enjoyed of Elliott Bay from the west side of the upper floors and Mount Rainier from the south side. The property is highly regarded locally and tenant occupancy has proceeded smoothly since construction was completed.

The Mitsui Fudosan Group’s long-term management policy, Vision 2025, includes the aim to evolve into a global company, and dramatic growth overseas is expected in the future. The Group is engaged in Asia, including China, Taiwan and Southeast Asia, in addition to the U.S. and U.K. In the U.S., Mitsui Fudosan is engaged in multiple developments including offices and housing. In March 2018, the Mitsui Fudosan Group took part in the Robinson Landing project, its first residential community (condominium and townhome) project in the Washington D.C. area. In addition, the development of 55 Hudson Yard office building in Manhattan will be completed during the current fiscal year. Business is expanding in multiple cities and Mitsui Fudosan aims to capture further business opportunities going forward.


Exterior view of West Edge Tower


View from the roof deck

■Features of the Project

Aiming to be a high-grade property suitable for its prime location, West Edge Tower is equipped with numerous amenities including an entrance lobby whose main feature is a light-filled atrium, a deck and barbecue area on the 8th floor, and a dog run, while the top floor has a tenant lounge, library and gym for workouts with spectacular views. Moreover, to enhance convenience for tenants and create liveliness for the property there are plans to invite retail and dining establishments to open on the first floor and a restaurant on the eighth floor.

The main targets are business people from their late 20s to 40s who work in the area and desire to live in the highly convenient city center, with a sub-target being empty nesters in their 50s.

Urban Visions, a developer based in Seattle that is involved in a wide variety of developments ranging from office and residential buildings in the city to renovations, is the joint developer.


Entrance lobby


Deck on the 8th floor

View from the gym on the top floor

West Edge Tower

Location 1430 2nd Avenue, Seattle, WA, U.S.
Access Three minutes on foot from University Street Station on the LRT Link Line (providing direct access to Seattle-Tacoma International Airport)
One to four minutes on foot from bus stops for various city bus lines
Site Area Approx. 19,000 ft2 (approx. 1,700 m2)
Total Floor Area Approx. 568,300 ft2 (approx. 52,800 m2)
Residential Space Total approx. 346,700 ft2 (approx. 32,200 m2)
Housing: Approx. 334,800 ft2 (approx. 31,100 m2)
Commercial: Approx. 11,900 ft2 (approx. 1,100 m2)
Units 340 units
Structure Reinforced concrete
Floors 39 floors above ground, 5 floors below ground
Purpose Rental housing and commercial facilities
Schedule Construction start: August 2015
Construction completion: April 2018

■Map

Map of the surrounding area

Detailed map

Click map to enlarge

Residential Developments in the U.S.

■East Coast

160 Madison Avenue <Completed>

Location 160 Madison Avenue, New York,NY
Completion September 2015
Site Area 21,500 ft2 (approx. 2,000 m2)
Total Floor Area 312,400 ft2 (approx. 29,000 m2)
Floors 42 above ground and 1 below
Purpose Rental housing (318 units)
Overview Mitsui Fudosan developed with joint developer from 2013

525 West 52nd Street <Completed>

Location 525 West 52nd Street, New York, NY
Completion May 2017
Site Area 38,100 ft2 (approx. 3,500 m2)
Total Floor Area 444,800 ft2 (approx. 41,300 m2)
Floors North Wing 22 floors with 1 floor below ground, South Wing 14 floors
Purpose Rental housing (392 units)
Overview Mitsui Fudosan developed with joint developer from 2015

4000 North Fairfax Drive <Under development>

Location 4000 North Fairfax Drive, Arlington County, VA
Completion 2020 (planned)
Site Area 26,000 ft2 (approx. 2,400 m2)
Total Floor Area 450,000 ft2 (approx. 42,000 m2)
Floors 22 above ground and 5 below
Purpose Rental housing (approx. 330 units (planned))
Overview Mitsui Fudosan developed with joint developer from 2017

1630 Colombia Road <Under development>

Location 1630 Columbia Road NW, Washington D.C.
Completion 2021 (planned)
Site Area Approx. 29,500 ft2 (approx. 2,700 m2)
Total Floor Area Approx. 230,400 ft2 (approx. 21,400 m2)
Floors 10 above ground and 2 below
Purpose Rental housing
Overview Mitsui Fudosan developed with joint developer from 2019

■West Coast

O&M <Completed>

Location 650 Indiana Street, San Francisco, CA
Completion August 2017
Site Area 26,300 ft2 (approx. 2,400 m2)
Total Floor Area 100,600 ft2 (approx. 9,300 m2)
Floors 5 above ground and 1 below (two buildings)
Purpose Rental housing (total 116 units)
Overview Mitsui Fudosan developed with joint developer from 2015

22 Texas <Under development>

Location 1395 22nd Street, San Francisco, CA
Completion 2019 (planned)
Site Area 120,447 ft2 (approx. 11,200 m2)
Total Floor Area 323,274 ft2 (approx. 30,000 m2)
Floors East building: 1 below ground and 4 above West building: 1 below ground and 8 above Commercial building: 1 below ground and 3 above
Purpose Rental housing (263 units)
Overview Mitsui Fudosan developed with joint developer from 2017

Walnut Creek Transit Village <Under development>

Location Block 1: 1701-1799 Pringle Avenue, Walnut Creek, CA Block 2: 1901-1915 N California Boulevard, Walnut Creek, CA
Completion Block 1: 2020 (planned) Block 2: To be determined
Site Area Block 1: 164,656 ft2 (approx. 15,300 m2)
Block 2: 182,516 ft2 (approx. 17,000 m2)
Total Floor Area Block 1: 593,782 ft2 (approx. 55,100 m2)
Block 2: 424,954 ft2 (approx. 39,400 m2)
Floors Block 1: 1 below ground and 4 above (two buildings)
Block 2: 2 below ground and 4 above (two buildings)
Purpose Rental housing (Block 1: 358 units; Block 2: 238 units)
Overview Mitsui Fudosan to develop with joint developer from 2018